Construction of the 19 km Spuzzum section of the Interior-Lower Mainland transmission line

Merritt-Coquitlam power line completed

A year behind schedule and over-budget, high-voltage line subject to arbitration between BC Hydro and its contractor

A year behind schedule and $18 million over budget, the latest high-voltage line of the BC Hydro grid has been completed from Merritt to Coquitlam.

The new line parallels the existing main line supplying the Lower Mainland and Vancouver Island from hydro dams on the Peace and Columbia Rivers. It was originally to be completed in 2014, but the main contractor fell behind and BC Hydro used its own crews to complete one of the most difficult portions, a 19 km stretch north of Hope.

The final cost for the 247 km line is expected to be $743 million, which Energy Minister Bill Bennett said is about two per cent more than the initial $725 million budget.

“There is an ongoing arbitration between BC Hydro and [contractor] Flatiron Graham as to who’s going to bear the cost of the delay, because the project was delayed by a year,” Bennett said in an interview Friday.

It’s the first 500-kilovolt line added to the BC Hydro grid in 40 years, to keep up with demand from a growing southwestern B.C. population and increase reliability in the event of disasters.

“You always have the potential for a big avalanche or a mudslide, even an earthquake, to take out one or two of your big transmission lines, bringing electricity in from the two rivers, the Columbia and the Peace,” Bennett said.

NDP energy critic Adrian Dix said the project started out with a $600 million estimate, making it $143 million over budget. He said it’s the latest in a series of cost overruns, including the Northwest Transmission Line north of Terrace, the Dawson Creek-Chetwynd line and the Iskut extension in the northwest.

Bennett said BC Hydro is under-budget on its overall capital construction plan, including $100 million under budget on reconstruction of five generating units at the W.A.C. Bennett Dam on the Peace River, and there is no additional effect on rates.

BC Hydro is committed to a capital budget of $2.4 billion a year for the next 10 years, including construction of the Site C dam on the Peace River and reconstruction of the Ruskin Dam in the Fraser Valley and the John Hart Dam on Vancouver Island.

 

Just Posted

Liquor licence to be pursued for West Fraser Centre

North Cariboo Joint Planning Committee voted unanimously to obtain liquor licence for Quesnel’s WFC

Barkerville opens for the season

Highlights of Barkerville’s upcoming season include 150th Dominion Day and pack train re-creation

Local couple spearheads Lewis Drive rink renovation

Revamped outdoor rink in West Quesnel will be of great use to families in all seasons

Standout athletes inducted into Quesnel Sports Hall of Fame for achievements in 2017

Local archers, swimmers, gymnasts and more recognized for gold-medal performances

Walk for MS this Saturday

Stop by Spirit Square to make a donation and get on the walking route

Police release video on how to ‘run, hide, fight’ if there’s an active shooter

Vancouver police offer video with input from E-Comm, BC EHS, Vancouver Fire and Rescue

Horgan defends fight to both retain and restrict Alberta oil imports

Alberta says pipeline bottlenecks are kneecapping the industry, costing millions of dollars a day

RCMP caution boaters after two kids pass out from carbon monoxide poisoning

Both children were given oxygen and taken to hospital

B.C. invests $115M to create 200 new nurse practitioner jobs

Health Minister says 780,000 B.C. residents don’t have a family doctor

Supreme Court rules social housing residents in B.C. deserve rights too

Tenants trying to stabilize their living situations should not face less legal rights than those paying market rates: Judge

Union calls on prime minister to step into ‘stalled’ Phoenix compensation talks

For more than two years, thousands of federal workers have been affected by Phoenix system

Judge: President Trump can’t block critics on Twitter

The judge had suggested that Trump mute rather than block some of his critics

NFL owners adopt new policy to address anthem protests

Commissioner Roger Goodell said the change was approved unanimously by owners

Mount Polley lockout an effort to speed up negotations company said

Mount Polley Mining Corporation’s labour agreement with United Steelworkers Local 1-2017 expired Dec. 31

Most Read