Construction of the 19 km Spuzzum section of the Interior-Lower Mainland transmission line

Merritt-Coquitlam power line completed

A year behind schedule and over-budget, high-voltage line subject to arbitration between BC Hydro and its contractor

A year behind schedule and $18 million over budget, the latest high-voltage line of the BC Hydro grid has been completed from Merritt to Coquitlam.

The new line parallels the existing main line supplying the Lower Mainland and Vancouver Island from hydro dams on the Peace and Columbia Rivers. It was originally to be completed in 2014, but the main contractor fell behind and BC Hydro used its own crews to complete one of the most difficult portions, a 19 km stretch north of Hope.

The final cost for the 247 km line is expected to be $743 million, which Energy Minister Bill Bennett said is about two per cent more than the initial $725 million budget.

“There is an ongoing arbitration between BC Hydro and [contractor] Flatiron Graham as to who’s going to bear the cost of the delay, because the project was delayed by a year,” Bennett said in an interview Friday.

It’s the first 500-kilovolt line added to the BC Hydro grid in 40 years, to keep up with demand from a growing southwestern B.C. population and increase reliability in the event of disasters.

“You always have the potential for a big avalanche or a mudslide, even an earthquake, to take out one or two of your big transmission lines, bringing electricity in from the two rivers, the Columbia and the Peace,” Bennett said.

NDP energy critic Adrian Dix said the project started out with a $600 million estimate, making it $143 million over budget. He said it’s the latest in a series of cost overruns, including the Northwest Transmission Line north of Terrace, the Dawson Creek-Chetwynd line and the Iskut extension in the northwest.

Bennett said BC Hydro is under-budget on its overall capital construction plan, including $100 million under budget on reconstruction of five generating units at the W.A.C. Bennett Dam on the Peace River, and there is no additional effect on rates.

BC Hydro is committed to a capital budget of $2.4 billion a year for the next 10 years, including construction of the Site C dam on the Peace River and reconstruction of the Ruskin Dam in the Fraser Valley and the John Hart Dam on Vancouver Island.

 

Just Posted

Column: this and that for seniors

Ruth Scoullar is back with her monthly round up of activities for seniors in Quesnel

‘Violent’ Prince George man wanted on Canada-wide warrant

RCMP say the man has likely made his way to the Lower Mainland or another community

Voter turnout at 25.5% in City of Quesnel; 16% in CRD

Both are lower than the provincial average of 36%

Official election results released for City of Quesnel

Two transcription errors were found, which did not affect candidate rankings

Local CRD candidates win by small margins; recounts not guaranteed

Chief election officer says recounts will only happen if number of rejected ballots were significant

B.C. sailor surprised by humpback whale playing under her boat

Jodi Klahm-Kozicki said the experience was ‘magical’ near Denman Island

B.C. government moves to tighten resource industry regulations

New superintendent will oversee engineers, biologists, foresters

Election watchdog seeks digitally savvy specialists to zero in on threats

Move follows troublesome evidence of online Russian interference in the 2016 U.S. election

More court before Dutch man charged in Amanda Todd case is extradited here

Appeals must be dealt with in Europe, before charges faced in B.C.

Crown says man guilty of B.C. girl’s 1978 murder based on alleged confession

Jury hears details of girl’s 1978 murder while Crown says man should be convicted of girl’s murder based on alleged confession.

BCHL alumni has NHL jersey retired by Anaheim Ducks

Paul Kariya played with the Penticton Vees from 1990-1992

Most Read