FILE – This Nov. 3, 2015 file photo shows the Keystone Steele City pumping station, into which the planned Keystone XL pipeline is to connect to, in Steele City, Neb. Pipeline sponsor TC Energy says it has started preliminary work along its route through the U.S. as opponents wait for a judge to rule on their request to block the project. (AP Photo/Nati Harnik, File)

Canadian firm starts US prep work for Keystone XL pipeline

Opponents await a judge’s ruling on their request to block any work

A Canadian company said Wednesday it has started preliminary work along the route of the proposed Keystone XL oil sands pipeline through the U.S. in anticipation of starting construction next month, as opponents await a judge’s ruling on their request to block any work.

TC Energy spokeswoman Sara Rabern said the Calgary-based company was moving equipment this week and will begin mowing and felling trees in areas along the pipeline’s 1,200-mile (1,930-kilometre) route within the next week or so.

The work is planned in Montana, South Dakota and Nebraska, Rabern said. She did not provide further location details.

ALSO READ: U.S. judge blocks construction of $10-billion Keystone XL pipeline

In April the company plans to begin construction at the line’s border crossing in northern Montana. That would be a huge milestone for a project first proposed in 2008 that has since attracted bitter opposition from climate activists who say fossil fuel usage must be curbed to combat global warming.

The company also plans work next month on employee camps in Fallon County, Montana and Haakon County, South Dakota.

Environmental groups in January asked U.S. District Judge Brian Morris to block any work. They said clearing and tree felling along the route would destroy bird and wildlife habitat. The judge in December had denied a request from environmentalists to block construction because no work was immediately planned.

The request by environmentalists came days after the Trump administration approved a right-of-way allowing the $8 billion line to be built across federal land.

ALSO READ: Alberta still pushing for Keystone XL pipeline after U.S. stoppage

“It is irresponsible for TC Energy to jump the gun before Judge Morris rules on our motion,” Stephan Volker, an attorney for the Indigenous Environmental Network and North Coast Rivers Alliance, said Wednesday.

Keystone XL was rejected twice under former President Barack Obama over worries it could make climate change worse.

The pipeline would transport up to 830,000 barrels (35 million gallons) of crude oil daily from western Canada to terminals on the U.S. Gulf Coast.

President Donald Trump has been a strong proponent. The Republican issued a special permit for the pipeline last year after Morris had blocked the project in November 2018, citing potential spills and other environmental concerns.

A legal challenge to Trump’s permit is pending before Morris.

ALSO READ: South Dakota Keystone XL opponents point to N. Dakota spill

Another oil pipeline in TC Energy’s Keystone network in October spilled an estimated 383,000 gallons (1.4 million litres) of oil in eastern North Dakota. Critics say a damaging spill from Keystone XL is inevitable given the length of the line and the many rivers and other waterways it would cross beneath.

Matthew Brown, The Associated Press

Like us on Facebook and follow us on Twitter

Keystone XL

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Visitor to Kamloops army club tests positive for COVID-19: Interior Health

The individual visited Anavets 290 Army and Navy Club between March 13 and March 17

‘An extra $220 every 90 days’: B.C. patients pay more dispensing fees due to prescription limits

Kelowna woman says it’s outrageous to charge for refills every 30 days

A grateful community

Another community convoy to thank health care workers is planned for April 5

Forestry Ink: Introduced, not invasive species

Columnist Jim Hilton writes about animals that are considered invasive

QUIZ: How much do you know about hockey?

Take this test and find out how well you know Canada’s most popular winter sport

QUIZ: How much do you know about hockey?

Take this test and find out how well you know Canada’s most popular winter sport

Two inmates found positive for COVID-19 at federal prison in B.C.; other tests pending

15 staff self-isolating waiting results, refusal to work notice sent, says correctional officer

Critic, workers’ group ‘disappointed’ Trudeau chose Amazon to distribute PPE

Amazon Canada said in an email to The Canadian Press that it is working with Canada Post, Purolator

How to cope with your mental health during a global pandemic

Becca Shears, clinical counsellor in Vanderhoof speaks about ways to deal with stress and anxiety during this time.

Full World COVID-19 update: National Guard collect ventilators in New York; Spain, Italy improve

Comprehensive coronavirus update with news from around the world.

Two people fined after B.C. police spot online ads re-selling 5,000 surgical, N95 masks

Police confiscated the masks, being sold at inflated prices, and now working with Fraser Health

Sex workers face new risks during COVID-19 pandemic

‘Desperation has kicked in’ for vulnerable, undocumented workers unable to access help

Most Read