Coastal GasLink stops work on section of pipeline route

Internal audit reveals clearing took place without valid archaeological impact assessments in place

Map of pipeline route showing location of Section 8 on which work has been stopped due to discrepencies with archaeological impact assessments. Coastal GasLink graphic.

Coastal GasLink (CGL) has stopped work on the last section of its pipeline project which runs from roughly south of Hazelton to Kitimat due to discrepencies with its archaelogical impact assessments.

In a statement on its website tonight, the company said it had discovered during an internal audit two areas where clearing has taken place in Section 8 contrary to its permits from the BC Oil and Gas Commission (OGC).

“At KP (kilometre post) 585, an area of approximately 600 metres long by 50 metres wide was cleared without an approved AIA in place,” the statement reads. “Areas adjacent to this location did have an approved AIA and were identified as low likelihood of archaeological significance. While clearing activities have taken place, minimal ground disturbance has occurred since the area has been used for transit and corduroy mats had been placed to limit disturbance.

READ MORE: NEB rejects federal review of Coastal GasLink pipeline

“At KP 631, due to a re-route, an area of approximately 240 metres by 10 metres was cleared without an AIA being completed. Areas adjacent to this location did have an approved AIA and were identified as low likelihood of archaeological significance”

CGL says it has voluntarily disclosed these incidents to (OGC), and the Environmental Assessment Office (EAO) and First Nations groups affected.

“Coastal GasLink is committed to protecting the environmental and cultural values of British Columbia during construction and operation of our natural gas pipeline,” said David Pfieffer, CGL president.

READ MORE: Gidimt’en launch civil lawsuit against Coastal GasLink

“Coastal GasLink regrets the errors that led to construction activities taking place without having approved archaeological impact assessments in place prior to start of construction.

“I have directed the team to complete a thorough investigation of these incidents and have halted clearing work in the area until the investigation is complete and recommendations are put into practice.

“I have also apologized to the impacted Indigenous communities and requested their participation in a proposed post-impact assessment.”



editor@interior-news.com

Like us on Facebook and follow us on Twitter

Just Posted

Military called in to remove inert practice round found in Quesnel industrial park

A maintenance worker mowing the grass found the round, which turned out to no longer be explosive

Ranch Musings: No-till pasture rejuvenation and sivopasture trials

Columnist David Zirnhelt is hosting a field day Aug. 29 in Beaver Valley

Meet Tour de North cyclist Chris Fedoruk

Quesnel man is a community rider with this year’s Cops for Cancer team

Forestry Ink: Forest tenure changes are occurring throughout the world

Regular columnist Jim Hilton writes about forest tenure and ownership

Quesnel Safeway honours its volunteer shoppers

This year marks the 20th anniversary of Safeway’s volunteer shopper program

Disney Plus to launch in Canada in November

Analysts say latest streaming service may escalate cord cutting

Okanagan bus driver assaulted for asking patron not to smoke

59-year-old in hospital with non-life threatening injuries

B.C. sets rules for ride hailing, same minimum fee as taxis

Larger operating areas seen as threat by cab companies

Two hiking families team up to extinguish fire in B.C. backcountry

Children and their parents worked for three hours to ensure safety of the popular hiking region

Vancouver man arrested after pregnant woman’s SUV stolen, then crashed

Police are recommending charges against a 22-year-old Vancouver man

Elections Canada to assess ‘partisan’ climate change rhetoric case by case

People’s Party of Canada Leader Maxime Bernier has said climate change is not an emergency nor caused by human

Unseasonable snow forces campers out of northeastern B.C. provincial park

Storm brought as much as 35 centimetres of snow to the Fort Nelson, Muncho Lake Park-Stone Mountain Park

B.C. log export rules killing us, northwest harvester says

NorthPac Forestry says Skeena Sawmills has plenty of timber

Most Read