Safety concerns prompt Highway 97 intersection improvements in Quesnel: MoTI

Traffic lights coming to Dragon Hill Road intersection, median to be installed
25233087_web1_201014-QCO-crash-forprint_1
Debris from a crash litters Highway 97. (Cassidy Dankochik file photo - Quesnel Cariboo Observer)

The province is moving forward on Highway 97 intersection safety improvements in Quesnel.

The project will involve widening 1.1 kilometres of Highway 97 and improvements to two key intersections along the eastern approach to the city.

Traffic signals will be installed at the intersection of Highway 97 and Racing Road/Dragon Hill Road, which has a historically high collision rate. The addition of signals will improve safety for all road users and provide better access to the local road network and adjacent businesses.

READ MORE: Two people, including a child, taken to hospital after crash on Highway 97

At Highway 97 and Quesnel Hydraulic Road, improvements will make it safer for drivers to turn off and onto the highway. The southbound left turn lane from Highway 97 onto Quesnel Hydraulic Road will allow more space for vehicles to slow down without impeding highway traffic. Left turns onto the highway southbound will be restricted.

A centre median will be installed along Highway 97 between the two intersections to separate opposing lanes of traffic and to better define the lanes when visibility and weather conditions are poor. New LED streetlights will be installed, as well as new drainage to remove surface water efficiently.

Utility relocations have already begun, and tendering will open in the coming weeks. With a successful tender, construction is anticipated to start in August 2021 and finish in fall 2022.

The ministry has investigated and confirmed the nearby Red Bluff slide will not impact this project.